Detailed Engineering Consultancy and Project Management for Railway siding from Mahegaon station on Jukhi – Kymore line in Jabalpur division of West Central Railway for ACC Limited
- Collected existing data, review all relevant existing literature, study reports
- Conducted in-depth discussions with key stakeholders (including ACC’s Engineering, Logistics & Plant Team) regarding projected traffic and to inform the planning of loading and unloading of wagons at a suitable location.
- Conducted route identification and selection of ‘optimum’ alignment design of plan and profile (L -Section) of new railway
- Conducted topographical, hydrological and geological studies
- Carried out a reconnaissance survey of the area to establish techno – economically alternative alignments for the Railway Line, including suitable take off points from the main line
- Recommended a suitable operational system for the smooth movement of logistics.
- Prepared Engineering Scale Plan for railways and detailed engineering designs including designs for earthworks, related structures, track, workshops, stations, electrification system, signalling and telecommunications and mechanical works
- Conducted detailed field engineering and prepared all necessary General Arrangement Drawings such as L-Section, Fixing of Alignment, laying of curve on grounds, benchmarking along the alignment, L-Section for earthwork in embankment and cutting, construction drawings for culverts, bridges, etc.
- Prepared drawings for major/minor bridges, culverts with detailed soil investigation and hydraulic study. Design of the embankment to suit local conditions
- Prepared the Bill of Quantities (BOQ) and all technical specifications including preparing detailed estimates for bridges, permanent way material, workshop, stations, mechanical, electrical and other rail infrastructure
- Conducted technical, economic and financial appraisals of different rail-based technologies along with related recommendations that are most suitable for the project.
- Prepared Detailed Project Report (DPR)
- Prepared the Signalling Interlocking Plan (SIP) and obtained approval.
- Prepared the Layout Plan of OHE (LOP)
- Prepared the Detailed Design of S&T
- Prepared the Detailed Design of OHE
- Necessary laisoning and obtained approval from Railways for installation of weigh bridge, track construction and land licensing.
- Prepared tender documents and provided necessary support in the procurement process including technical bid evaluation and reporting.
- Project Management and Construction Supervision
- Established detailed construction /erection methodology, execution plan and work schedule with construction contractors to match with the overall project schedule
- Reviewed and approved work method and procedure in line with contract requirement and engineering practice
- Reviewed and approved the contractor’s designs.
- Finalized the construction code, standards and specifications etc. with construction contracts and engineering standards specifications and approved drawings
- Reviewed construction schedule of contractors and held review meetings to monitor the trend in schedule and progress
- Reviewed site mobilization plan and monitored mobilization of required personnel, resources and equipment
- Checked initial and final level for execution of work
- Prepared monthly progress reports/exception reports highlighting the percentage completion of work, areas of concern with respect to schedule to be deployed.
- Reviewed the Contractor’s construction and quality assurance plan and confirmed its compliance
- Finalized the inspection and test plan
- Audited and approved welding procedures and welder’s qualification procedure
- Arranged and advised on track testing and trial runs
- Organized inspection of completed works
- Monitored safety procedures by construction contractor
- Audited documentation submitted by the construction contractor periodically
- Provided oversight regarding the necessary arrangements for required field inspection and tests
- Submitted inspection procedures for review/approval
- Vetted As-Built Drawings submitted by the contractor
- Provided certification of measurements/milestone progress of site work
- Provided any other activities relevant to construction management
Feasibility Study, DPR, ESP and Detailed Engineering Study and Designs:
Construction Plans & Procedures:
Construction Monitoring
Construction Management & Quality Assurance:
Construction Inspection:
Service/Sub-Service Tag
- Detailed Design
- Detailed Engineering
- Feasibility Study
- Project Management and Construction Supervision
- Site Investigations
- Survey
- Value Engineering